Question # 23

A milestone must “finish no later than” September 30 due to regulatory reporting. Which constraint description is MOST accurate?

Options:

A.

It sets the earliest permissible finish date

B.

It sets a latest allowable finish; finishing earlier is acceptable

C.

It forces the activity to finish exactly on September 30

D.

It automatically adds float to the critical path

Viewing question 23 out of 71 questions
Industry research shows that students who utilize CAPM practice tests are significantly more likely to pass exam.


Our free CAPM practice questions act as a diagnostic tool to give you a clear snapshot of your Certified Associate in Project Management readiness. Discover which topics are your strengths and, more importantly, which critical topics require your immediate attention.