Question # 19

In Critical Chain Project Management (CCPM), which buffer primarily protects the overall project completion date from variability on the longest chain of dependent tasks?

Options:

A.

Feeding buffer

B.

Project buffer

C.

Resource buffer

D.

Management reserve

Viewing question 19 out of 71 questions