Question # 17

Which statement BEST contrasts CPM and PERT in schedule development?

Options:

A.

CPM uses probabilistic durations; PERT uses deterministic durations

B.

CPM focuses on resource leveling; PERT ignores uncertainty

C.

CPM typically uses single-point deterministic estimates; PERT uses three-point (optimistic, most likely, pessimistic) to compute expected durations

D.

CPM is only for construction; PERT is only for software

Viewing question 17 out of 71 questions