Question # 60

A support team faces unpredictable arrival of work items and wants to visualize flow, limit WIP, and reduce cycle time. Which approach fits BEST?

Options:

A.

Scrum with fixed two-week sprints and velocity tracking

B.

Kanban with explicit WIP limits and continuous delivery

C.

Extreme Programming with pair programming focus

D.

Hybrid Scrum-Waterfall with stage gates