Question # 56

A team wants to visualize work-in-progress, identify bottlenecks, and observe flow stability over time. Which artifact is MOST appropriate?

Options:

A.

Sprint burndown chart

B.

Cumulative Flow Diagram

C.

Velocity chart

D.

Product roadmap

Viewing question 56 out of 71 questions