Question # 57

Which statement correctly distinguishes total float from schedule reserve?

Options:

A.

Both are interchangeable buffers used anywhere in the schedule

B.

Total float is added by management outside the network; schedule reserve emerges from network logic

C.

Total float is the path/activity flexibility from network calculations; schedule reserve is a management buffer added to protect dates and controlled via change control

D.

Schedule reserve belongs to sellers; total float belongs to buyers

Viewing question 57 out of 71 questions