Question # 63

Your team’s Cumulative Flow Diagram shows the “In Review” band widening over the last three sprints while “Done” lags. What is the BEST first action?

Options:

A.

Increase WIP limits to push more work through

B.

Establish/ tighten WIP limits at “In Review,” swarm to clear the queue, and address process/policy causes

C.

Add overtime to accelerate reviews

D.

Split stories after development to make review faster

Viewing question 63 out of 71 questions