Question # 6

A night-shift operator cannot clock out until the day-shift operator clocks in. Which precedence relationship BEST models this?

Options:

A.

Finish-to-Start (FS)

B.

Start-to-Start (SS)

C.

Start-to-Finish (SF)

D.

Finish-to-Finish (FF)