Question # 2

Mid-planning, you introduce a 3-day lead between two FS activities on the critical path to compress the schedule. What is the BEST immediate next step?

Options:

A.

Add a 3-day buffer at project end to protect the date

B.

Recalculate the network to identify the new critical/near-critical paths and update float

C.

Increase contingency reserve by 3 days for those tasks

D.

Fast track additional pairs of activities for more savings

Viewing question 2 out of 71 questions