Question # 10

Which set of components correctly makes up the Scope Baseline?

Options:

A.

Project Charter, WBS, and Requirements Documentation

B.

Scope Statement, WBS, and WBS Dictionary

C.

Scope Management Plan, WBS Dictionary, and Change Log

D.

Requirements Traceability Matrix, WBS, and Schedule Baseline

Viewing question 10 out of 71 questions