Question # 4

Given BAC = 900,000, CPI = 0.90, and SPI = 0.80, and assuming both cost and schedule inefficiencies will persist, what is the BEST EAC forecast?

Options:

A.

900,000

B.

1,000,000

C.

1,125,000

D.

1,250,000

Viewing question 4 out of 71 questions
Industry research shows that students who utilize CAPM practice tests are significantly more likely to pass exam.