Question # 41

Mid-sprint, a line manager bypasses the Product Owner and assigns two Developers “urgent” work. What is the BEST action for the Scrum Master?

Options:

A.

Direct the Developers to comply to maintain relationships

B.

Escalate immediately to the steering committee for discipline

C.

Coach the manager and team to route all new work through the Product Owner; protect the Sprint Goal and facilitate renegotiation only if the goal remains achievable

D.

Replace the Sprint Goal with the urgent request

Viewing question 41 out of 71 questions