Question # 44

Your CPI is unreliable because several large change requests were just approved and re-estimation of the remaining work is underway. Which EAC method is MOST appropriate?

Options:

A.

EAC = BAC / CPI

B.

EAC = AC + (BAC − EV)

C.

EAC = AC + Bottom-Up ETC

D.

EAC = BAC / (CPI × SPI)

Viewing question 44 out of 71 questions
Industry research shows that students who utilize CAPM practice tests are significantly more likely to pass exam.


Our free CAPM practice questions act as a diagnostic tool to give you a clear snapshot of your Certified Associate in Project Management readiness. Discover which topics are your strengths and, more importantly, which critical topics require your immediate attention.