Question # 29

In Earned Value Management, which index indicates cost efficiency of the work performed, and how is it calculated?

Options:

A.

SPI = EV / PV

B.

CPI = EV / AC

C.

CV = EV − AC

D.

SV = EV − PV

Viewing question 29 out of 71 questions