Question # 6

Project monitoring shows multiple tasks slipping on the critical path. What should the project manager do?

Options:

A.

Ignore since overall progress is acceptable

B.

Reassess schedule and apply compression techniques where appropriate

C.

Ask the sponsor to extend deadlines automatically

D.

Remove non-critical tasks without analysis

Viewing question 6 out of 72 questions