Question # 2

The project schedule shows multiple tasks delayed due to dependency bottlenecks. What should the project manager do?

Options:

A.

Remove dependencies without analysis

B.

Reassess critical path and explore fast tracking or crashing options

C.

Extend deadlines without consulting stakeholders

D.

Cancel non-critical tasks

Viewing question 2 out of 72 questions