Question # 9

A deliverable passes internal quality checks but is rejected by the customer. What should the project manager do?

Options:

A.

Deliver it anyway

B.

Revalidate customer requirements and acceptance criteria

C.

Escalate to sponsor for resolution

D.

Ask the team to redo without analysis

Viewing question 9 out of 72 questions