Question # 11

A new stakeholder challenges the project scope late in execution. What should the project manager do?

Options:

A.

Ignore since scope is baselined

B.

Listen to concerns, assess impact, and process through change control if necessary

C.

Escalate directly to the sponsor

D.

Ask the team to implement changes quietly

Viewing question 11 out of 72 questions