Question # 3

A stakeholder requests a change that may significantly extend the schedule. What should the project manager do?

Options:

A.

Accept and implement the change immediately

B.

Evaluate impact on schedule, cost, and scope, then process through change control

C.

Refuse all changes to protect baseline

D.

Ask the sponsor to decide without analysis

Viewing question 3 out of 72 questions