Question # 44

The project team is dispersed across multiple time zones, leading to poor collaboration. What should the project manager do?

Options:

A.

Require everyone to work during the same time zone

B.

Establish overlapping working hours and use collaboration tools effectively

C.

Assign tasks only to co-located members

D.

Ignore since delays are minor

Viewing question 44 out of 72 questions