Question # 45

Stakeholders request urgent scope changes that may impact quality. What should the project manager do?

Options:

A.

Approve changes immediately

B.

Conduct impact analysis on cost, schedule, and quality, then follow change control

C.

Reject all changes to protect baseline

D.

Implement changes informally to save time