Question # 47

A new compliance requirement introduces additional documentation tasks. What is the project manager’s first step?

Options:

A.

Refuse the requirement because it wasn’t in the baseline

B.

Conduct impact analysis and update plans accordingly

C.

Ask the sponsor to decide whether to comply

D.

Ignore since it increases workload