Question # 39

A project milestone is missed due to underestimated effort. What should the project manager do first?

Options:

A.

Escalate to sponsor immediately

B.

Reassess estimates, update the schedule, and evaluate corrective actions

C.

Ignore since milestones often shift

D.

Cancel activities to recover time

Viewing question 39 out of 72 questions