Question # 37

The organization shifts focus to digital transformation. Your project is paper-based. What should the project manager do?

Options:

A.

Continue execution since baselines are fixed

B.

Evaluate alignment and propose changes through business case review

C.

Cancel the project immediately

D.

Deliver current outputs and let operations digitize later

Viewing question 37 out of 72 questions