Question # 23

A project’s earned value analysis shows SV = –20, CV = +15. What does this indicate?

Options:

A.

Project is ahead of schedule and over budget

B.

Project is behind schedule but under budget

C.

Project is on track

D.

Project is behind schedule and over budget

Viewing question 23 out of 72 questions