Question # 19

Two departments have competing resource demands, delaying project work. What should the project manager do?

Options:

A.

Reassign resources without consulting departments

B.

Use conflict resolution and negotiate priorities with department managers

C.

Escalate to sponsor immediately

D.

Allow departments to decide without PM involvement

Viewing question 19 out of 72 questions