Question # 18

Cost performance index (CPI) = 1.05, schedule performance index (SPI) = 0.95. What does this mean?

Options:

A.

Over budget, behind schedule

B.

Under budget, behind schedule

C.

Under budget, ahead of schedule

D.

On track in both cost and schedule