Question # 21

The government introduces stricter labor laws that impact your project’s resource planning. What should the project manager do?

Options:

A.

Continue using existing plans

B.

Perform impact analysis and update resource plans to comply

C.

Escalate to sponsor and shift responsibility

D.

Ignore until audit occurs

Viewing question 21 out of 72 questions