Question # 51

Early massing studies show two viable forms. The owner wants the lower-cost option if performance remains strong. What’s the best integrative next step?

Options:

A.

Defer decisions until CDs to avoid rework

B.

Run quick parametric energy + daylight “shoebox” tests and a preliminary water balance for both forms; capture targets in the OPR/BOD and carry winning strategies into specs

C.

Choose the cheaper form now and fix performance later with premium equipment

D.

Ask vendors to propose equipment first, then shape the building around it

Viewing question 51 out of 71 questions