Question # 48

After the earliest energy and water analyses are complete, which step best ensures the design continues to reflect the owner’s performance goals through CDs and into construction?

Options:

A.

Focus on prescriptive checklists and ignore the early analysis outputs

B.

Update the OPR and BOD with measured performance targets; embed requirements in specs (controls sequences, metering points), and review at milestones with the CxA

C.

Rely on vendor submittals to “optimize” performance during procurement

D.

Postpone performance decisions until after occupancy surveys

Viewing question 48 out of 71 questions