To support monitoring-based commissioning, which metering scheme is most appropriate for a mixed-use building?

Options:

A.

Read the main utility meter monthly and estimate end uses

B.

Install advanced whole-building meters for each energy source and permanent sub-meters for major end uses ≥10% of total consumption (e.g., HVAC plant, lighting, plug/process), logging interval data

C.

Use temporary meters during the first season only

D.

Rely on thermostat histories to infer energy use

Viewing question 27 out of 71 questions