Question # 66

A supplier misses a critical delivery date on the critical path. What should the project manager do next?

Options:

A.

Immediately apply liquidated damages per the contract

B.

Update the issue log and perform schedule impact analysis before deciding on responses

C.

Replace the supplier and re-baseline the schedule

D.

Ask the team to work overtime to compensate, without analysis

Viewing question 66 out of 72 questions