Question # 64

Your project is aligned with corporate sustainability goals. Midway, the sponsor asks you to cut cost by eliminating sustainability-related features. What should you do?

Options:

A.

Remove features immediately to satisfy the sponsor

B.

Explain strategic alignment and facilitate impact assessment before any decision

C.

Ignore sponsor’s request and proceed

D.

Delay decision until project closure

Viewing question 64 out of 72 questions