Question # 56

A project deliverable is delayed because of unclear acceptance criteria. What should the project manager do first?

Options:

A.

Deliver the work anyway to stay on schedule

B.

Review and clarify acceptance criteria with stakeholders

C.

Escalate the issue to the sponsor immediately

D.

Ask the team to decide criteria informally