Question # 55

Leadership changes the project’s expected benefits mid-execution. What should the project manager do?

Options:

A.

Continue without adjustment

B.

Reassess benefits, update the business case, and align with leadership

C.

Cancel the project independently

D.

Delay action until closure

Viewing question 55 out of 72 questions