Some engineers are completing an activity that will alert the project team if there is a risk of requiring additional effort to complete the project. What should the risk manager do in case the trigger arises?

Options:

A.

Activate the contingency plan.

B.

Request a reserves increase.

C.

Add the alert to the risk register.

D.

Update the risk response plan.