Question # 57

A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project's technical debt and meet the project deadline.

What should the risk manager advise the project manager to do to address this situation?

Options:

A.

Immediately hire as soon as the project begins to fall behind schedule.

B.

Hire as soon as the project metrics trigger a risk response.

C.

Only hire when it is economically feasible to do so.

D.

Only hire if risk response is escalated and approved by the stakeholders. 

Viewing question 57 out of 74 questions
Industry research shows that students who utilize RMP practice tests are significantly more likely to pass exam.


Our free RMP practice questions act as a diagnostic tool to give you a clear snapshot of your PMI Risk Management Professional (PMI-RMP) readiness. Discover which topics are your strengths and, more importantly, which critical topics require your immediate attention.