Question # 24

A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.

What should the project manager do next to avoid similar risks?

Options:

A.

Add contingencies to other tasks to mitigate similar risks.

B.

Reassess risks with a new assumptions and constraints analysis.

C.

Review the risk response plan looking for lessons learned.

D.

Log the event in the issue log and update the project management plan.

Viewing question 24 out of 74 questions
Industry research shows that students who utilize RMP practice tests are significantly more likely to pass exam.


Our free RMP practice questions act as a diagnostic tool to give you a clear snapshot of your PMI Risk Management Professional (PMI-RMP) readiness. Discover which topics are your strengths and, more importantly, which critical topics require your immediate attention.