Question # 22

The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends.

How should the project manager and the risk manager handle this situation?

Options:

A.

Ensure the project complies with the current traffic regulations and laws.

B.

Send a letter to the traffic authority with the general project information.

C.

Perform inquiries on the website of the traffic authority weekly.

D.

Meet with the traffic authority staff in charge of the new regulation.

Viewing question 22 out of 74 questions
Industry research shows that students who utilize RMP practice tests are significantly more likely to pass exam.


Our free RMP practice questions act as a diagnostic tool to give you a clear snapshot of your PMI Risk Management Professional (PMI-RMP) readiness. Discover which topics are your strengths and, more importantly, which critical topics require your immediate attention.