Question # 67

During construction, what plan best protects IAQ and simplifies turnover?

Options:

A.

Store absorptive materials uncovered in active work zones to speed access

B.

Implement a Construction IAQ Management Plan: protect/cover absorptive materials, use proper filtration on operating equipment, control sources, maintain housekeeping, and document with photos/inspections

C.

Disable filters to maximize airflow during dusty work

D.

Rely on a short flush-out only after move-in

Viewing question 67 out of 71 questions