Question # 64

During construction on a tight site, how should topsoil be handled to protect ecological function and future planting success?

Options:

A.

Strip and dispose of topsoil off-site to simplify staging

B.

Salvage, stockpile under cover with perimeter controls, keep piles out of drainage paths, and specify post-construction soil restoration (decompaction and organic amendments)

C.

Mix topsoil with construction debris and spread it later

D.

Leave stockpiles uncovered; rainfall will keep them moist

Viewing question 64 out of 71 questions