Question # 56

After the kickoff charrette, what is the most integrative, low-cost way to keep decisions evidence-based through schematic design?

Options:

A.

Pause analysis until CDs to avoid rework

B.

Run quick “shoebox” energy studies and a preliminary water balance each week; update OPR/BOD and specs with targets; have the CxA verify at milestone check-ins

C.

Let vendors propose substitutions at bid time for savings

D.

Focus only on HVAC efficiencies and revisit envelope later

Viewing question 56 out of 71 questions