Question # 49

A project team has completed the risk response plan for a newly identified major project risk. Some team members argue the plan does not totally eliminate the risk, considering the effort required to implement it, and feel the planned response should be thrown out altogether.

What should the risk manager do in this situation?

Options:

A.

Accept the response because there are no secondary risks were identified.

B.

The response plan should be discontinued and the risk should be accepted and dealt with if it occurs.

C.

Accept the residual risk as it is compatible with the organization's risk appetite.

D.

All identified risks must be addressed because they might significantly impact the project if they occur. 

Viewing question 49 out of 74 questions
Industry research shows that students who utilize RMP practice tests are significantly more likely to pass exam.


Our free RMP practice questions act as a diagnostic tool to give you a clear snapshot of your PMI Risk Management Professional (PMI-RMP) readiness. Discover which topics are your strengths and, more importantly, which critical topics require your immediate attention.