Question # 32

A project team successfully implemented a risk response plan for a major risk event. Residual risks were evaluated and actions were taken to keep them under control. There were no secondary risks after the implementation.

What should the risk manager do?

Options:

A.

Study the change logs to implement the approved change requests.

B.

Close out the expired risk and update the relevant project documents.

C.

Get permission from stakeholders before documenting lessons learned.

D.

Continue monitoring the critical response plan on the delivered product.

Viewing question 32 out of 74 questions