Question # 3

Cooling towers were added late in design. To minimize potable water use and operating risk, which plan is most credible?

Options:

A.

Run constant blowdown and accept high water bills

B.

Analyze make-up water quality to set cycles of concentration, install conductivity-based controls for blowdown, meter make-up and blowdown, use efficient drift eliminators, and integrate tower data into the BAS for alerts

C.

Use once-through potable water for condenser cooling when it’s hot

D.

Turn towers off during peak months to save water regardless of load

Viewing question 3 out of 71 questions