Question # 14

Which pairing correctly aligns early-phase documents and responsibilities in the Integrative Process?

Options:

A.

OPR written by the contractor; BOD by the owner; CxA verifies during punch list only

B.

OPR authored by the owner team, BOD by designers translating OPR into technical criteria, CxA engaged early to review alignment through design and construction

C.

OPR skipped; BOD created after occupancy; CxA hired for warranty claims

D.

OPR created by vendors; BOD drafted by the commissioning agent; designers follow vendor selections

Viewing question 14 out of 71 questions