Question # 61

You are asked to prepare a cost estimate early in schematic design. Which type of estimate is most appropriate?

Options:

A.

Detailed quantity takeoff with unit costs

B.

Square-foot or unit-area cost estimate based on benchmarks

C.

Guaranteed Maximum Price (GMP) proposal

D.

Final bid estimate from contractors

Viewing question 61 out of 72 questions