Question # 37

A contractor requests clarification on conflicting dimensions between the planting plan and the irrigation plan. What is the best immediate course of action?

Options:

A.

Direct the contractor to proceed with whichever dimension seems most logical

B.

Issue a Supplemental Instruction (ASI) or clarification sketch resolving the discrepancy

C.

Instruct the contractor to halt all site work until a change order is processed

D.

Defer the decision until the end of construction

Viewing question 37 out of 72 questions