Question # 20

A municipality asks you to create a scope, schedule, and budget for a neighborhood park renovation. Which deliverable most appropriately defines task durations, dependencies, and critical path before design begins?

Options:

A.

Work Breakdown Structure (WBS) with Gantt chart

B.

Design development cost estimate

C.

Change order log

D.

Final punch list

Viewing question 20 out of 72 questions